NewsDriving Tampa Bay Forward

Actions

Tampa protected bikeway extended sooner than expected

Stormwater improvements also going in on Cass St.
Posted at 5:19 AM, Oct 02, 2018
and last updated 2018-10-02 06:01:10-04

TAMPA, Fla. — Downtown Tampa’s protected bikeway, the Green Spine cycle-track, will be extended sooner than expected into West Tampa.

 A new stormwater improvement assessment fee approved by Tampa City Council in September allows the city to proceed with its Cypress Street Outfall Extension project. 

To avoid ripping up the road twice, the City of Tampa has decided to build the Green Spine at the same time it installs a new box culvert that will drain the road after heavy rains. 

The project is located on Cass Street between Rome and Boulevard, and along Rome Avenue from Kennedy to Cass.

By tying Green Spine Phase 2 in with the stormwater work, the opportunity has been created for the Green Spine Phase 3B segment to be next in line for available grant funds.

Phase 3B will run along Nuccio Parkway from Nebraska Avenue to 7th Avenue and now prioritized as the first segment to be funded for construction. 

The City of Tampa will design and construct the remaining western segment from Boulevard across the Cass Street Bridge to Gasparilla Plaza with its own funds.